Project's context & challenges
At a waste-to-energy plant in central Italy, a customer needed to pasteurize the digestate flow for further processing, while using a minimum amount of heat.

Key figures
10 m³/h
system
>90%
heat recovery
Customer benefits

Reliable pasteurization, high availability

Low energy use due to included heat exchanger and heat recovery

Pre-commissioned before transport, low impact on site.
Solution
Byosis delivered and installed the ByoPast® unit consisting of 3 pasteurization vessels for a continuous flow of 10 m3/hr. The system was adapted to customer-specific parameters, such as the viscosity and dry matter content of the process water. During the initial months of operation, Byosis provided guidance on system operation and cleaning, as well as on ensuring optimal and reliable performance.

Scope of supply
- Design and engineering of ByoPast®
- Supply of all equipment, internals and tanks
- Installation, commissioning and project management
- Start-up and training of operators
Applied solutions
- ByoPast® container with controls and balance of plant components
- Heat exchanger and heat recovery
- 3 pasteurization vessels incl interconnecting piping